DrydenBridgeConstruction1

Construction workers install rebar and form on the south end of the South George Road bridge.

The Dryden Town Council offered an update on the construction taking place on South George Road to replace the bridge. This is one of two projects from the 2016 Bridge NY program. In 2017, the town received $3.64 million in funding from the New York State Department of Transportation to fund the construction projects for the South George Road bridge and the one-lane bridge along Freese Road.

The Town Council offered the following timeline of the construction that has occurred so far on South George Road:

Feb. 18: Superstructure Removal

Construction workers removed the asphalt wearing surface and the wood bridge deck with an excavator. After removing the deck, the crew used the excavator as well as a crane to remove the large wood stringers that were underneath.

Feb. 19: Substructure Removal

Using a crane, the workers removed the bridge’s substructure, which was made out of wood piles and beams. The crew also cut up and removed the steel sheet piling that is used for building abutments to connect with the deck and provide horizontal and vertical support.

Feb. 20–24: Structure Excavation 

Excavation of the south end of the bridge took place behind the existing steel sheet piling. A concrete abutment and wingwalls were constructed. Three inches of stone was set to assist with pile driving. The same process was done on the north end of the bridge as well.

DrydenBridgeConstruction#2

The south end of the South George Road bridge after excavation.

March 3: Drive Culverts

The construction crew replaced the existing 12-inch culverts on the west side of South George Road – north of the bridge – and replaced them with a 12-inch High-Density Polyethylene (HDPE) pipe with metal-end sections.

March 5: Pile Driving

On the south end, workers drove steel H-piles for the abutment and wingwalls, creating 35-inch depths in the neighborhood, according to the report.

March 10: Concrete Abutment

Piles were driven and trimmed at two inches above grade. Rebar and forms were placed for the abutment wall on the south. Concrete abutment was poured on to the piles.

March 12: Pile Driving

The crew begins the same pile-driving process from the south end on the north end of the bridge. According to the report, this process is still in operation.

DrydenBridgeConstruction#3

Steel H-piles driven on the north end of the South George Road bridge.

Traffic along South George road is closed for the time being as construction continues. The bridge is anticipated to reopen in late October.

 

Sports Editor

Andrew is the sports editor as well as a news reporter for the Ithaca Times/Finger Lakes Community Newspapers. He also enjoys writing personal essays in his spare time.

(0) comments

Welcome to the discussion.

This is a space for civil feedback and conversation. A few guidelines: 1. be kind and courteous. 2. no hate speech or bullying. 3. no promotions or spam. If necessary, we will ban members who do not abide by these standards.